Project:
Titan America Penk5 Cement Plant
Client: Titan America LLC
Location: Medley, Florida
Construction Period: 2003 – 2004
Zachry began work on the Pennsuco Modernization Project
in 2003. The project required Zachry to design and build
a new 5,000 tons-per-day cement plant and furnish balance
of plant utility engineering and construction services
for Titan America.
The new dry-process cement plant was designed to produce
a higher-quality product for Titan America’s customers,
lower production costs, and reduce emissions to the
environment. The Pennsuco Modernization Project has
been called an “industry milestone” because
of its rapid progression from conception to completion.
Zachry completed construction of the multimillion-dollar
project in April 2004, two months ahead of schedule.
The 5,000 tons-per-day facility replaces two wet process
lines. The existing cement grinding facilities, along
with the existing cement storage and handling systems,
will remain in place in support of the new plant.
Titan management attributes the Pennsuco project construction
success to a combination of strong teamwork, intelligent
engineering and sound scheduling. F.L.Smidth and Zachry
both praised Titan America for early site preparation
and for pre-project planning that contributed to the
project’s success.
The project was not without its share of challenges,
however. Because of the high water table in Florida,
Zachry had to pump out thousands of gallons of water
before pouring the concrete. At one point, Zachry was
pumping 12,000 gallons of water per minute to enable
the concrete pour.
Despite the challenge posed by the shallow water table,
Zachry was able to pour the foundations for the preheater
by February 2003, and was out of deep water by mid-May
2003.
Zachry credits much of their success to the Zachry
Project Execution Planning Process ® (ZPEPP), a
project management system that maintains focus on the
execution plan. Zachry’s team of experienced workers
also contributed to increased efficiencies during the
construction phase of the project. We estimate that
80 percent of the project’s workers, many of them
from the local area, had worked on prior Zachry jobs.
That experience – and the workers’ enthusiasm
at being asked to work for Zachry again - contributed
to an efficient and safe project. |