Dallas High Five Project Ahead of Schedule
> Segment Erector Demo
(Flash movie by Dallas Morning News)
August
25, 2003
(Dallas, Texas) – The
Dallas High Five Interchange is setting records beyond those
of its height and scope as a construction project. Texas Department
of Transportation’s Northwest Area Engineer for Dallas
County Larry Tegtmeyer announced the five-level interchange
project at the intersection of U.S. 75 and I-635 is ahead
of schedule.
“We officially began the project January
2, 2002,” he said. ”We’re one year into
the program, and while that’s 20 percent of the contract
time, construction is 28 percent complete.”
Contractor Zachry Construction will be paid
an incentive for every day the project is completed in less
than five years, up to a maximum of one year early. They will
be charged liquidated damages for every day the project completion
exceeds five years. Approximately one-third of the five-year
construction project takes place at night. It is scheduled
for completion by the end of 2006.
Dallas High Five Interchange Project
Facts:
- The $261 million Interchange is the largest
single highway project ever awarded in Texas. When completed,
the five levels will include:
- Level 1 – Four lanes of travel
northbound and southbound U.S. 75
- Level 2 – Frontage Road Box (named
for the rectangular shape created by the intersection of
continuous east-west and north-south frontage roads through
the Interchange)
- Level 3 – Five lanes of travel
eastbound and westbound I-635 and two lanes each way barrier-separated
HOV lanes on I-635
- Level 4 – Direct Connection Ramps
from U.S. 75 to I-635
- Level Five – Direct Connection
Ramps from I-635 to U.S. 75 and Reversible HOV Lanes to/from
I-635 west and U.S. 75 north
First-year accomplishments on the $261 million
project include:
- Bridge columns are 45 percent complete
with 322 completed out of 710 total
- Bridge Caps – 187 completed or
46 percent of 409 total
- Bridge Beams – 46,862 linear feet
or 29 percent have been set out of 163,619 total
- Pre-cast Bridge Segments–
130 erected or 21 percent of 623 total
The project has reached a number of construction
milestones and more are scheduled for completion in 2003,
which include:
- Westbound LBJ frontage road from TI Boulevard
to Cottonwood Creek – complete at the end of March
2003
- Southbound North Central Expressway frontage
road from Midpark Road to Coit Road – complete in
late March 2003
- TI Access Bridge - complete late summer
2003
- Coit Road Bridge - complete by August
2003
- Direct connector eastbound LBJ to northbound
North Central Expressway – complete in November 2003.
(This is the completion of the first direct connector)
The big yellow and blue Segment Erector
is the first of its kind in the U.S. It was designed and constructed
by Deal S.R.L. of Italy.
Deal is a subsidiary of Rizzani de Eccher,
an Italian company with whom Zachry Construction has partnered
to design and build the segmental portions of the direct connection
ramps. The erector weighs 101 tons and measures 97 feet long
by 38 feet wide by 37 feet tall and cost approximately $1
million to build.
The Segment
Erector is being used to hoist pre-fabricated
bridge segments into place on bridges as part of the High
Five construction. It is capable of lifting a load of 70 tons
from the ground to the top of the pier at the rate of 30 feet
per minute. Once the segment is on the top, the erector can
travel from end to end of the cantilevered pier at a rate
of 0.45 mph. This ability to lift the segments from either
end of the cantilever and travel with it to the point of placement
is the unique characteristic of this erector. This ability
has greatly minimized the impact to the traffic traveling
underneath.
The article
contains information from a Texas Department of Transportation
press release (www.dot.state.tx.us/txdot.htm).
<<
Return to list of news stories >>
|